U.S. Supreme Court Broadly Interprets Filed Rate Doctrine: Entergy Louisiana, Inc. v. Louisiana Public Serv. Comm'n
On Monday June 2, 2003, the United States Supreme Court issued its opinion in
Entergy Louisiana, Inc. v. Louisiana Public Serv. Comm'n, Docket No. 02-299, strongly endorsing the principle of exclusive federal jurisdiction under the Federal Power Act. The unanimous
decision addresses the on-going battle between energy market participants and state and federal regulatory bodies over who
gets the last word on setting energy rates, and which participant in the energy market will ultimately bear the costs of power.
The decision affirmed the Federal Energy Regulatory Commission's ("FERC") exclusive authority to set wholesale energy rates,
and made clear that states may not reevaluate FERC-approved rates, but rather must allow utilities to pass along to retail
ratepayers the costs incurred under FERC-approved wholesale rate schedules.
Settled case law under the Federal Power Act, including widely-cited U.S. Supreme Court precedent, provides that the FERC
has exclusive authority to determine the reasonableness of wholesale rates. This means that when an electric utility purchases
power from a wholesale provider, only FERC can decide if the price charged is fair. Once the FERC decides that a wholesale
price is fair, a long line of cases also provides that the utility may pass along those wholesale costs to its ratepayers.
While the FERC regulates wholesale energy rates, state public utility commissions regulate retail rates. Because state public
utility commissions set retail rates, utilities must forward a variety of types of cost information to state commissions,
which then decide whether those costs may be included in computing the retail rates paid by ratepayers as part of a prudence
or reasonableness review process.
This case arose when a state public utilities commission decided not to allow a utility to pass on to retail ratepayers discretionary
costs the utility incurred under a FERC-approved rate schedule. The state-regulated electric utility, Entergy Louisiana, Inc.
("ELI"), bought wholesale power from its parent company, Entergy Corporation, under a FERC-approved rate schedule. The rate
schedule allowed Entergy Corporation to decide how to share costs among its various generating and transmission facilities
in four states. FERC approved this cost-sharing plan and made it a part of the FERC-approved rate schedule because it found
that allowing Entergy Corporation to balance costs resulted in a system-wide savings to the generators, as well as an overall
benefit to utilities and ratepayers. However, FERC also found that under the rate schedule certain utilities (including ELI),
and thus certain ratepayers, would be paying more than their appropriate share based on Entergy Corporation's cost sharing
decisions.
When the state public utility commission (here, the LPSC) set ELI's retail rates, the LPSC decided not to allow ELI to pass
along certain costs ELI had incurred under the FERC-approved schedule. The LPSC found that it was "imprudent" for ELI to knowingly
pay more than its share for power. The LPSC decided that, because Entergy Corporation could have made different choices under
the FERC-approved schedule that would not have forced ELI to pay more than its share, ELI should have resisted Entergy Corporation's
decision to continue forcing ELI to pay more than its share under the FERC-approved plan.
ELI appealed the LPSC's decision to the Louisiana Supreme Court, which affirmed the LPSC's decision. The Louisiana Supreme
Court held that the LPSC decision "did not challenge[] ELI's decision to participate in the [FERC-approved] Agreement. Rather,
the LPSC has merely examined the prudence of ELI's failure to . . . minimize its payments [by challenging Entergy Corporation's
decisions]." ELI then petitioned the United States Supreme Court for review. The Court's decision on Monday squarely rejected
the Louisiana Supreme Court's reasoning, and made clear that utilities may recover via retail rates all costs, whether mandatory
or discretionary, incurred under a FERC-approved rate schedule.
The LPSC had advocated that the Supreme Court recognize an exception to the filed rate doctrine, which requires that state
utility commissions give binding effect to all interstate wholesale power rates filed with or fixed by FERC. The filed rate
doctrine, as well as settled case law, also provide that utilities may pass along to ratepayers costs incurred under a FERC-approved
rate schedule. The exception the LPSC sought would have distinguished between mandatory and discretionary costs under FERC-approved
rate schedules. Such an exception would have permitted state commissions to disallow utilities from recovering discretionary
costs incurred under FERC-approved rate schedules if the commission found the costs were "imprudent."
In Monday's decision, the Supreme Court declined to make such an exception, stating "We see no reason to create an exception
to the filed rate doctrine for tariffs of this type that would substantially limit FERC's flexibility in approving cost allocation
arrangements." The Court also ruled that a state commission may not "second-guess" the FERC about "how and by whom" decisions
regarding cost allocation under FERC-approved rate schedule should be made.
The Court also rejected the notion that FERC's exclusive jurisdiction was not implicated because FERC had not specifically
approved the cost allocation at issue. The Court noted its prior holdings that "the view that the preemptive effect of FERC
jurisdiction turns on whether a particular matter was actually determined in the FERC proceedings has long been rejected."
Thus, the LPSC's second-guessing of the cost allocation issues was preempted.
This case not only determined that public utility commissions may not second-guess FERC-approved rates, but also reinforces
the continued vitality of the filed rate doctrine and the preemptive effect of FERC's exclusive jurisdiction over wholesale
electricity markets.