Texas Governor Greg Abbott has directed the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) to conduct a comprehensive verification and audit of all data centers advancing through ERCOT’s interconnection process. See “Governor Abbott Directs Comprehensive Data Center Audit.”
The PUCT and ERCOT must complete this audit before any data center project moves forward. Any project that fails to comply with the requirements set forth by the PUCT and ERCOT will be denied connection to the Texas grid.
This order will disrupt projects that are currently underway and challenge the ability of parties to existing transactions involving the construction of data centers to comply with the terms of their contractual obligations. Parties to such transactions should consider enhanced monitoring of their counterparties’ performance—and potentially reevaluate in-service dates and timelines—considering the impacts that this order and further activity by the PUCT and ERCOT in response to it will have.
According to the governor’s statement, ERCOT is currently considering over 474 GW in requests to connect to the Texas grid — 90% of which are for data centers. To put this figure in context, Texas’ hourly peak demand reached a historical record of 91.1 GW on July 22, 2026, surpassing the previous record of 85.5 GW. Such unprecedented load growth, coupled with ongoing regulatory reforms (such as the potential transition from 4CP to 12CP), could endanger the reliability and stability of the Texas electric grid.
The governor has also directed the PUCT and ERCOT to obtain the following information from each data center project:
The order raises many questions, including whether the order has any effect on projects outside of the ERCOT territory or projects that rely exclusively on on-site “behind-the-meter” generation, and how the order will affect implementation by ERCOT of its “Batch Zero” process for large loads just announced in June. See “ERCOT Trending Topics.”
In reaction to the order, ERCOT has already announced that the notification it previously indicated would be provided by August 7 related to the classification of projects as “base load,” “studied load,” and “excluded” will not be issued by that time. See “M-A080326-01 Update Regarding Batch Zero Timelines and Processes.” Instead, ERCOT will be seeking a good cause exception from the PUCT at its August 20 meeting related to the timelines and process for Batch Zero.
Morrison Foerster has represented clients in numerous transactions involving data center construction in Texas and other locations, including:
The governor’s order raises numerous questions with respect to how projects that are currently underway will be impacted and the ability of parties to comply with existing contractual terms, including:
Our multidisciplinary team of Data Center and Digital Infrastructure lawyers works with data center developers, operators, lenders, and investors around the globe. We have advised some of the most active and sophisticated stakeholders in the data center space on their projects.
Drawing on the capabilities of our Austin office and our multidisciplinary Data Center and Digital Infrastructure team, we are available to assist you in evaluating the impact of Governor Abbott’s order on your Texas transactions and projects. Please reach out to: